Page 45 - Studio International - May 1969
P. 45

the Merzbarn. In May 1965 the wall was    liminary survey.                           7 This steel framework, which has two lift-
          thoroughly surveyed by Mark Lancaster,    2 The wall is shored up inside and out, all   ing eyes welded into the top of it, was shut-
          David Wise and myself, under the supervision   the points of contact being insulated against   tered and filled with concrete. The size of the
          of Richard Hamilton, then on the staff at   vibration with two inches of expanded poly-  piece of wall we took was about twelve feet by
          Newcastle. John Laing Limited of Carlisle   styrene. I spent much of my time sitting on   nine.
          were the contractors and they moved in on   the shoring with my finger on the face of the   8 Next a gantry was put up over the site,
          July 12, 1965. I went too, as a representative   plaster, feeling for tremors.       carrying an enormous lifting gear. All this
          of the Department, my job being to pick up   3 Joe Barlow working on the outside. The   steelwork had to be manhandled up the track
          the pieces if the worst happened.         inner wall was exposed in sections about two   to the site and put up with a pole and a block
          The Merzbarn is made of plaster applied   feet square at a time. The stones were grouted   and tackle. The weather was wet and got
          directly to a rough drystone wall, and rein-  with a strong mortar and then left to set while   wetter as the critical part of the job ap-
          forced with sticks, canes, string and the like.   work continued on another part of the wall.   proached.
          It could not be taken to pieces and re-   4 A course of `throughs' supported by wire   9 All set to go. Through the window is one
          assembled in its new home, it had to be taken   and wooden props while the grouting set. At   of Schwitters' collection of oddly-shaped stones.
          in a piece. The system which Laings proposed   the bottom of the picture is one of the boulders   10 On September 22 the Merzbarn began
          was to embed in concrete the backs of the   which formed the foundations of the barn.   to move. The weight of the wall was taken
          stones which carry the plasterwork, in order   These went too deep into the ground to be   on the lifting tackle which was then run back-
          to make the whole thing secure so that it   moved and to clear them the wall had to be   wards along the gantry, tipping the wall and
          could be moved safely. This plan was com-  cut 14 inches above floor level.          lowering it into a horizontal position.
                                                                                                   The foot of the wall was wedged to pre-
          plicated by the double structure of the wall.   5 The back of the wall with the first stage   11
          Like all the walls in that district it was in fact   well advanced. In the centre is one of the   vent its slipping forwards. In this picture one
          two walls side by side with a rubble filling   invaluable Acrow expanding props. These   can see how much of the work was lost be-
          between and occasional courses of `throughs',   could be easily moved around to apply sup-  cause of the boulders. Also notice how near to
          broad stones laid across the two walls tying   port to the wall as the work progressed. In the   the face of the wall are the uprights of the
          the whole structure together. The outer wall   foreground is the heap of stone taken from the   gantry. It was an extremely difficult job to
          had to be removed to reach the back of the   wall.                                   handle these huge weights so close to the fra-
          inner wall. The pictures explain the process   6 	Some of the `throughs' coincided with the   gile plaster.
          better than words.                        steel frame which was put up behind the wall   12 	Safely down, the wall is being sheeted up
             The scene of operations. The barn in Mr
          1 	                                       and had to be cut. We used an impregnated   against the rain. Subsequently Pickfords' men
          Pierce's garden with the Langdale Pikes in   fibre saw, which makes less vibration than a   arrived to transport the wall to Newcastle.
          the background. The work itself is on the far   toothed saw, but nonetheless this was an   13 Pickfords used hydraulic jacks (that is
          wall opposite the door. The bank behind it   anxious time, since the plaster of the relief was   one in the left foreground), rollers, a winch
          has been excavated in the contractors' pre-   applied directly to the other end of this stone.    and six men to move the sixteen-ton mass. A
   40   41   42   43   44   45   46   47   48   49   50